This project was previously done in a semi-mechanized way by previous vendors and the time period for completion was around one month’s time, in which the company had to shutdown the cooling towers which resulted in time, resources and most importantly cost loss of production. We executed this job in the following methodology, which gave us appreciations and tremendous results in terms of time, cost and resource savings. Also, now this method is being used since then by the industry as we completed the project within a week\u2019s time.<\/span><\/p>1) We did not take the shutdown of the entire cooling tower but cleaned the plant on a cell by cell basis.<\/span><\/p>2) Dewatering of the basin to lower the water content was a continuous process<\/span><\/p>3) We used heavy duty truck mounted Vacuum Suction machines (super sucker) with hydraulic operated hopper having capacity of 20kl to suck the sludge from the basin into the hopper directly.<\/span><\/p>\t\t\t\t\t\t<\/div>\n\t\t\t\t<\/div>\n\t\t\t\t\t<\/div>\n\t\t<\/div>\n\t\t\t\t\t\t\t<\/div>\n\t\t<\/section>\n\t\t\t\t